Departments |
|
|
RAIL DEPARTMENTThis section consists of 4 technological lines, of 97 employees working in 2 shifts and is attended to a PFISTER concreting plant with 20 concrete meshworks. |
![]() |
|
The section produces 30 types of rail useful for small, double and standard gauge track repairs and constructions. |
|
|
MISCELLANOUS DEPARTMENT This department consists of 143 employees working in 7 producing area such as : |
![]() |
|
-sections field, executes prefabs for rolling tracks, railway tunnels, roof girder sections, different ferro-concrete prefabricated units for art works and various civil building prefabs; |
|
|
-centrifuged poles, manufactures prestressed and ferro-concrete poles by centrifugal action, poles that are being used for railway electrification, for underrunning voltage and mean stress power transmission and for tram and trolleybuss line support; |
|
|
-masonry section, performs various masonry products and precast boards using granulated and concrete blast-furnace slag; |
|
|
-rack, has 7 lines for manufacturing causeway bridge girders and prestressed concrete railway girders with a 3-33m gamma length adherent string; |
|
|
-hard precast field, specialized in manufacturing precast ferro-concrete up to 40 tones; |
|
|
-carpentry section, specialized and equipped for producing and maintaining the wooden gauge; |
|
|
-steel benders section, executes steel and concrete reinforcements. |
|
|
MECANO-ENERGETICS DEPARTMENT |
![]() |
|
-first workshop, produces and distributes the process steam- necessary for precast concrete thermal treatment-, and the compressed air; maintains unit’s all calorific equipment; |
|
|
-second workshop, deals with metal garments (execution, maintenance and metal gauge repairs); |
|
|
-third workshop, maintains and repairs the electrical wiring. This section consists of the following fields: coiling, electrical wiring repairs for electric mechanic equipment and radio components, as well as electromotors hoisting units repairing; |
|
|
-fourth workshop, executes chip removing processed metal works used for various cars and technological equipment; |
|
|
-fifth workshop, deals with concreting plants maintenance; |
|
|
-sixth workshop, maintains the gravel pit gradation plant and supplies the concreting plants with graded crushed rocks. |
|
|
EQUIPMENT TRANSPORT DEPARTMENT |
![]() |
|
-ballast extraction, where the ballast is extracted, deposited and loaded up; |
|
|
-transport column, which transports the ballast from the gravel pit to the unit precincts; transports the green concrete; provides the technical supplies; carries out special means activities (crane, bulldozer, and dragline); delivers the products to beneficiaries; |
|
|
-gradation unit, sieves out, flushes out and crushes the ballast preparing it for concrete manufacturing; |
|
|
-finished products warehouse, takes in and stores the products; loads up and secures them for transport and delivering. |
|